NHS blunder delays Multiplex hospital opening a year

1
476

Multiplex’s £150m Edinburgh children’s hospital will open more than a year later than planned, due to problems with the facility’s building services caused by a tender error.

Remedial work could add £90m to the construction cost, and follows an earlier £11.6m payout to the contractor over build standards.

The first patients had been due to move into the new Royal Hospital for Children and Young People (RHCYP), built by the IHS Lothian consortium, made up of Multiplex, Bouygues E&S FM, architects HLMAD and Macquarie Capital, in July this year.

However the move was delayed after it was discovered that issues with the ventilation system in the critical care facility at the hospital did not meet national standards. A series of tests were commissioned to check the facility met the relevant technical specifications and guidance.

Now a review of the governance arrangements for RHCYP by KPMG has found that the main issue with the ventilation stemmed from an error in a tender document produced by NHS Lothian in 2012. The document stated that the ventilation system for the single-bed cubicles and four-bed rooms in the critical care unit needed to be capable of four air changes per hour, when in fact they should have been capable of 10 air changes per hour.

The KPMG report blamed human error and confusion over interpretation of standards and guidance and also concluded that opportunities to spot and rectify the error were missed.

A range of issues with the building’s ventilation system, including additional problems in the oncology and haemotology departments and problems with the hospital’s water systems, need to be fixed before a phased move into the hospital. The Department of Clinical Neurosciences (DCN) is now expected to move in in spring 2020, with the rest of the children’s hospital moving to the new site in autumn 2020.

The Scotttish government’s health secretary Jeane Freeman said: “I am of course bitterly disappointed that a mistake made in 2012 was not picked up earlier. This is a publicly funded project of strategic importance, which has not been delivered by NHS Lothian in compliance with the standards and guidance. The delay we now face will be borne by NHS Lothian staff, by patients and their families and the additional cost will be to the public purse.

“My overriding priority is that the children and families who depend on these hospital services can receive them in the safest way possible. The current situation is not one anyone would chose – but it is one I am determined to resolve.”

The hospital cost £150m to build but an Audit Scotland report published in August found that the problems meant it would cost an additional £90m. A further £11.6m has already been paid out to IHS Lothian to end a dispute over construction standards at the hospital, which has been built under the Non-Profit Distributing system – a private financing model similar to PFI. Audit Scotland now estimates the total price tag for the hospital over its lifetime to be £520m.

Source:Construction Manager

got-a-story-2



Readers like you, make ESHADOOT work possible. We need your support to deliver quality and positive news about India and Indian diaspora - and to keep it open for everyone. Your support is essential to continue our efforts. Every contribution, however big or small, is so valuable for our future.

Click on below ‘Donate’ button to pay with PAYPAL Donation.


1 COMMENT

  1. In the climate of distrust when a Cient or their appointed consultant writes specification and in some cases ambiguous one such mistakes to the cost of public purse are likely to happen. Contractually for such a big project the bidder takes the risk however when there is fundamental error from Client’s side no one can foot the bill. Hopefully the remedial works will put things right and the needy children will get the treatment

LEAVE A REPLY